Determine whether a MOHRE temporary work permit is the correct authorization for a worker to perform a specific time-limited task at a registered establishment and complete the employer application without confusing it with a one-mission permit.
Choose the permit by the worker’s status, not by the word “temporary”
The UAE labour framework has several different work permits. A temporary work permit is for a worker employed for a job whose execution or completion falls within a specific period at an establishment registered with MOHRE. A one-mission permit is different: it lets a registered establishment recruit a worker from outside the UAE for temporary work or a defined project.
| Situation | Likely route to test | Why |
|---|---|---|
| Worker is already tied to another UAE employer and will do a defined short task for a second establishment | Temporary work permit | MOHRE’s temporary-permit service expressly addresses a specific task/period and current-employer approval. |
| Establishment is bringing a worker from abroad for a defined temporary project | One-mission permit | The implementing regulation assigns recruitment from outside for temporary work to this permit. |
| Ongoing reduced-hours work for more than one employer | Part-time route may be closer | The legal object is recurring part-time employment, not merely a finite task. |
Ordinary eligibility and employer-side requirements
MOHRE’s service card says the worker must generally be at least 18; regulated professions must satisfy the profession-specific licence rules; the proposed occupation must fit the establishment’s licensed activities; the establishment must hold a valid licence and not be suspended; and the application must come from its authorised signatory.
The official document list includes a passport copy valid for at least six months, a photo, the MOHRE job-offer form signed by employer and worker, qualification evidence for relevant skill levels and a professional licence where required.
Current-employer consent and the labour-court exception
The ordinary temporary-permit route requires electronic approval by the worker’s current employer. MOHRE states an exception for employees whose labour complaints have been referred to court. A complaint merely filed with MOHRE is not treated here as equivalent to a court referral.
Ministerial Resolution No. 47 of 2022 also permits a worker to seek a temporary permit with a new employer during the labour case, but excludes the worker reported under the stated unexpected-work-abandonment branch. The evidentiary question is therefore not “is there a dispute?” but “is there a documented court referral, and does the limitation apply?”
Consent / court-case exception map
| File state | Consent position | Evidence to establish |
|---|---|---|
| Ordinary temporary-permit application | Current-employer electronic approval required | MOHRE electronic approval plus job-offer/file documents |
| Labour complaint referred to court | MOHRE service card states an exception to current-employer approval, subject to the stated controls | Court/referral document and MOHRE case status |
| Unexpected-work-abandonment report applies | Do not assume the court-case temporary-permit route remains available | MOHRE absence/abandonment status and case record |
Fees, timing and the duration trap
MOHRE currently lists an AED 50 federal fee and a two-working-day service-completion target for a complete application. The same live service page is internally inconsistent on duration: it defines the permit as work for a specific task within a specified period and says a new application can be made when the permit expires, but it also displays a generic field reading “Permit Duration: Two Years.”
Current external mobility guides from Futura and Expatica describe a six-month temporary permit. That external material is useful evidence of the public-information conflict, but it cannot override a contradictory live official service card. For planning purposes, do not rely on either a two-year or six-month duration without checking the MOHRE approval/issued permit or obtaining current MOHRE confirmation. The issued authorisation and its stated expiry should control the operational timetable.
Operational sequence
- Write down the task, expected end point, worksite/entity and worker’s current immigration/employment status.
- Rule out the one-mission route if recruitment is from abroad.
- Obtain current-employer approval, unless a documented court-case exception applies.
- Collect the MOHRE job offer and qualification/professional evidence.
- The prospective establishment files through MOHRE/Tasheel channels and answers any shortfall request.
- Do not start covered work until the permit is issued and its scope has been checked.
Next legal state
- When the temporary engagement ends and the labour record must be closed: Work permit cancellation.
Primary and verification sources
Rules and service data can change. The material propositions above were checked against the following sources on 23 September 2026.
- Federal Decree-Law No. 33 of 2021 Regarding the Regulation of Employment Relationship and amendments — MOHRE / UAE federal law
- Cabinet Resolution No. 1 of 2022 – Executive Regulations of Federal Decree-Law No. 33 of 2021 — MOHRE / UAE Cabinet
- Issuance of a New Work Permit – Temporary Work Permits — MOHRE
- Ministerial Resolution No. 47 of 2022 — MOHRE
- Temporary Work Authorization Options for Students — Fragomen